The District uses contractors listed with MRSC Rosters for small works projects. Larger projects are published in the Seattle Daily Journal of Commerce and on our website.


PROJECTS IN PROGRESS:

Watermain Replacement - Ballinger Way NE - 37th to 40th

Status: Design and Engineering

This Project will replace 1300ft of 6" failing steel pipe with 12" ductile iron and will include a new vault with reverse check valve to allow increased fire flow and pressure reducing valve to reduce water aging.

Wellhead Area Security Improvements

This project improves local security of the wellfields with monitoring and surveillance.

Ballinger Roundabout

As part of the roundabout construction on Ballinger and 40th, our watermain requres relocation. Design has been completed and this will be constructed as part of the City's project by their contractor in 2026 and 2027.

 

 


Zone Metering

We are currently installing water flow meters throughout the distribution system that enable us to monitor system demand in various pressure zones. This integrates with our telemetry system to provide real-time and historical information to better operate and diagnose issues in the system.

 

 


Zone Metering Monitoring

COMPLETED PROJECTS:

McKinnon Creek Pumphouse Phase I

Phase I which included pipe, ducting and grading is complete. Work completed by D&G Backhoe. 2020

McKinnon Wellfield Perimeter Fence Repair and Replacement

Bid from MRSC Roster - Contract with Discount Fence (discountfencewa.com), Marblemount, WA. Work completed 1/2020

Watermain Repair

Emergency leak repair required excavation equipment. (B&B Utilities)  12/2019

Sidewalk Repair

Replace several concrete sidewalk panels following leak repair on watermain. (Small works project awarded to B&B Utilities 2020)

McKinnon Wellfield Tree Removal

Bid from MRSC Roster - Contract with Best Tree Services NW Inc. - Work completed.

Well 2 - Pump Replacement and well Rehab

Due to a nearby lightning strike, the pump motor suffered damage and required replacement. During the replacement the well was cleaned, surged, and inspected. (Small works project awarded to JKA Drilling $30,150 - Jan 2019)

Well 1 - Pump Replacement

After having exceeded it's life expectancy, this project replaced the worn and failing pump in our primary well. (Small works project awarded to PumpTech $17,100 - Oct 2017)

NE 178th St - '#3713 to #3369'

A pipe replacement project to upgrade existing deteriorated watermain and avoid conflict with the City of Lake Forest Park's improvements. Over 1000' of 2" HDPE watermain was installed and construction was managed cooperatively and concurrently with the City's construction.

NE 178th St and 180th St

This project replaced a failed valve cluster and upgraded watermain crossing 180th in preparation for the 178th St. watermain replacement.

Horizon View Backup Well Project - Brightwater- completed 3/14

Construction of backup wells, pump station, and transmission main to mitigate against potential Brightwater Tunnel leakage.

  • Phase I of this project is complete. Trail widening and utility infrastructure to site.
  • Phase II is completed and the system is currently supplying supplemental water to the district.

Ballinger Way PRV - Completed 4/13

Replacement of an aging and malfunctioning Pressure Reducing Valve (PRV) chamber that supplies water to the lowest zone in the district, the 'Beach Zone'.  The new PRV chamber is located at the intersection of Ballinger Way and 175th