| Article Index |
|
Minutes 2011
|
|
January 17, 2011
|
|
January 20, 2011
|
|
January 24, 2011
|
|
January 26, 2011
|
|
February 3, 2011
|
|
February 14, 2011
|
|
March 21, 2011
|
|
April 18, 2011
|
|
May 16, 2011
|
|
June 3, 2011
|
|
June 6, 2011
|
|
June 10, 2011
|
|
June 20, 2011
|
|
June 27, 2011
|
|
June 28, 2011
|
|
July 18, 2011
|
|
July 30, 2011
|
|
August 15, 2011
|
|
August 19, 2011
|
|
September 7, 2011
|
|
September 12, 2011
|
|
September 28, 2011
|
|
October 10, 2011
|
|
November 14, 2011
|
|
November 28, 2011
|
|
December 12, 2011
|
|
All Pages
|
Page 8 of 27
LAKE FOREST PARK WATER DISTRICT BOARD MEETING MINUTES MARCH 21, 2011
Commissioners present: Timothy Davis, Dr. Julie Hungar.
Others present: F. Alan Kerley, General Manager; Dan Mundall, Engineer, Richard Jonson, Attorney, Larry Bailey, Executive Director of the Water and Sewer Risk Management Pool, Dwayne Hatfield, Partner at Coram Deo Consulting Group Inc. Resident: James Apsitis
The meeting was held at the District office.
Mr. Davis called the meeting to order at 9:03 am.
The commissioners approved the agenda.
Dr. Hungar moved approval of the Feb. 14th 2011 special meeting minutes. Mr. Davis seconded. Motion passed.
Dr. Hungar moved that the selection process for appointing a new commissioner until the next election include an application, background check and if necessary a formal interview. Mr. Davis seconded. Motion passed.
Dr. Hungar moved that the District accept applications for Commissioner Position Number 3 until April 15th. 2011. Mr. Davis seconded. Motion passed.
Mr. Kerley gave the following General Manager’s report:
Meter reading and billing was completed on time.
We have received two new water availability requests.
Tom Steenmeyer has installed a permanent ladder on the standby tank. He is now working on the fabrication of a new railing system and then will complete the hatch retrofit and the cleaning and disinfection of the tank.
We have had our initial meeting with Baber and Mason. They are the CPA firm that we have hired to monitor our internal controls.
Phase IV construction may begin on short notice. We are prepared. The District has hired a temporary employee for construction inspection. His name is Mick Holte and his estimated time of employment is for two months.
All of the recent rain and saturation has led to several customer calls for potential leaks. So far everything has been groundwater. We will continue to monitor the problem areas.
In-house water sample testing continues to be of great benefit to the District. We have been able to test the sampling points for coliform bacteria one day prior to taking State required testing.
A discussion was then held regarding the City of Lake Forest Park 100-year legacy proposed trail. Staff was directed to write an inquiry letter about the proposed two phase plan that the District sent the city. Mr. Mundall gave the following updates:
Brightwater tunnel status: He believes that the boring machine will be under our aquifer in mid-July. At this time the District will need extra staffing and monitoring.
The Backup Wells: We are waiting on the purchase of the SPU property to become finalized.
PWTF Phase IV: The winning bid came in at $464,426.73. The engineer’s estimate was $600,000. If there is a remaining balance on the loan it will be used to replace the watermain on 30th Ave NE and/ or a PRV vault at the wellhead.
Richard Jonson of the Law Offices of Jonson and Jonson proposed an alternate rate structure to the board.
At 10:00 am, Mr. Davis called an executive session for approximately 45 minutes to discuss personnel matters. Mr. Apsitis then left the meeting.
At 10:48 am, the executive session was concluded and the regular session of the meeting was reconvened.
There being no other business the meeting adjourned at 11:00 AM.
|