| Article Index |
|
Minutes 2011
|
|
January 17, 2011
|
|
January 20, 2011
|
|
January 24, 2011
|
|
January 26, 2011
|
|
February 3, 2011
|
|
February 14, 2011
|
|
March 21, 2011
|
|
April 18, 2011
|
|
May 16, 2011
|
|
June 3, 2011
|
|
June 6, 2011
|
|
June 10, 2011
|
|
June 20, 2011
|
|
June 27, 2011
|
|
June 28, 2011
|
|
July 18, 2011
|
|
July 30, 2011
|
|
August 15, 2011
|
|
August 19, 2011
|
|
September 7, 2011
|
|
September 12, 2011
|
|
September 28, 2011
|
|
October 10, 2011
|
|
November 14, 2011
|
|
November 28, 2011
|
|
December 12, 2011
|
|
All Pages
|
Page 10 of 27
LAKE FOREST PARK WATER DISTRICT BOARD MEETING MINUTES MAY 16, 2011
Commissioner present: Dr. Julie Hungar.
Others present: F. Alan Kerley, General Manager; Dan Mundall, Engineer, Richard Jonson, Attorney, Residents: Bill Donahue
The meeting was held at the District office.
Call to Order Dr. Hungar called the meeting to order at 9:02 am.
The commissioner approved the agenda.
Approval of Minutes Dr. Hungar moved approval of the April 18 2011 board meeting minutes. Seconded and approved.
Approval of Vouchers Dr. Hungar moved approval of vouchers 112101 through 112163 totaling $44,616.25. Seconded and approved.
General Manager’s Report Mr. Kerley gave the following report:
Account balances through the end of April were: Maintenance-$96,909.01, Capital Improvement- $295,493.70 PWTF- $358,565.82,Market Savings-$28,564.04 Backup Well Fund- $1,539,372.68, Petty Cash-$ 503.25 Revenue Bond- $28,320.69
Staff and I have completed the installation of a new water service at address 18464 47th Pl NE.
The March/April reading and billing cycle was completed on time.
Phase IV construction is now underway. The contractor has installed 600 feet of new watermain. Current work is on the directional boring portion of the project.
The draft copy of the revised Employee Guide is ready for review and input.
Our scanner/fax machine is having trouble. I will be deciding if it is cost effective for the District to continue supporting this particular model.
Our new riding mower is still having problems. Further warranty work has been scheduled with Sears.
In spite of our mower troubles, the staff has been keeping up with all of the spring growth and the watershed and facilities look great.
State water sampling for the month of May has been completed. Annual water samples, which will include lead and copper, will be taken in June.
Dan and I have completed some needed improvements on the shallow well system.
A discussion was held regarding the Professional Services Roster.
Engineer’s Report Mr. Mundall gave the following Report:
100-Year Legacy Trail-. No change.
The Backup Wells: We are waiting on the purchase of the SPU property to become finalized. There may be a need to breakdown some of the construction items to allow offsite work. This will help ensure that the District meets certain timeline requirements. He is working on construction plans and permit applications for road widening and water main installation.
Mr. Jonson stated that he has been working with Pree Carpenter from Seattle Public Utilities on the purchase and sales agreement and conveyance deed. Progress is slow.
PWTF Phase IV: An easement issue was resolved by means of a legal survey. Also the preferred order of construction on the project near 18725 40th Pl NE is to install the HDPE pipe first and then the Ductile iron.
WHPA new pump facility: A discussion was held regarding a conditional use permit.
Ballinger Way Watermain Replacement 184th St.-178th St.: The project has been advertised and a site visit has been scheduled for May 18th. Bids close on May 25th. Engineers Estimate-$350,000.
Seattle Public Utilities wholesale water contract renegotiation: Awaiting Seattle City Council approval. There are minor issues with Exhibit 1 of the agreement that are being resolved with S.P.U.
Brightwater tunnel status: The Tunnel Boring Machine is in the critical part of our aquifer. We are currently set to a constant flow pump rate and telemetry monitoring has been increased.
Unfinished Business The Commissioner appointment process and timeline being considered by King County was discussed.
No change on the status of the remainder of the unfinished business items. New Business The Cedar River Water and Sewer District have asked us for a contribution for their efforts on the King County Growth Management Planning Council. In the past LFPWD has contributed $100.00 annually. Dr. Hungar motioned that we match last year’s contribution. Seconded and approved.
A conversation was held regarding the timeline for the District’s Comprehensive Plan. Mr. Jonson stated that revisions to the District’s water rights should be coordinated with the plan and work would need to resume later this year with the Dept. of Ecology to seek the revisions.
Mr. Mundall presented a schedule containing financial projections based on capital expenditures.
At 10:40 am, an executive session to discuss personnel issues was called for approximately 5 minutes. Mr. Donahue then left the meeting.
The executive session was ended at 10:43 am and the regular meeting was reconvened.
There being no other business the meeting adjourned at 10:43 AM.
|