|
The District maintains a Small Works Roster and a Professional Services Roster. To be included on the list, please see our forms.
PROJECTS IN PROGRESS:
Horizon View Backup Well Project - Brightwater
Construction of backup wells, pump station, and transmission main to mitigate against potential Brightwater Tunnel leakage.
---Phase I of this project is complete. Trail widening and utility infrastructure to site.
---Phase II is nearing completion. (5/10/2013) All of the elements are in place, and the system has undergone startup. Final landscaping and finish will occur as weather permits. We anticipate bringing the new wells into the system shortly.
RECENTLY COMPLETED PROJECTS:
|
Ballinger Way PRV - Completed 4/13
Replacement of an aging and malfunctioning Pressure Reducing Valve (PRV) chamber
that supplies water to the lowest zone in the district, the 'Beach Zone'. The new PRV
chamber is located at the intersection of Ballinger Way and 175th.
Backup Wells Phase I - Transmission main, offsite services, trail widening
Ballinger Way NE (NE 184th St to NE 178th St.) - Completed 9/11
Nearly 1500ft of 12" ductile iron replacing 6" steel to increase fire flow to mall
Intermediate Zone Improvements Phase IV - Completed 8/11
Wellhead Area - Replace 130ft of 6" steel with 8" ductile iron on hillside
Wellhead Area - Horizontal direction drill and open trench 900ft of new water main
NE 185th St - Replace 360ft of water main and pressure reducing valves
40th PL to 188th St - Nearly 1000ft of new main and pressure reducing valves
182nd PL NE - Over 3500ft of Water Main Replacement - Completed 9/10
High Zone Steel Standpipe Refurbish - Completed 4/10
Includes installation of mixing manifold to avoid stagnant water and tank repainting
NE 187th PL - Completed 9/09
Watermain replaces 360ft of asbestos-cement pipe with ductile iron and HDPE
NE 47th PL Cul-De-Sac - Completed 5/09
Watermain replaces 300ft of corroded steel pipe with ductile iron and HDPE
|
 |
|
|
| Contract Total By Schedule |
|
|
|
Bid Value |
Ext 8/10/11 |
|
|
Ext. 8/23/11 |
|
Ext. 9/9/11 |
|
Total Payments |
Diff. |
% Diff |
Contract Total By Schedule |
|
RRJ Company |
|
Taylors Excavating |
|
Marshbank Const. |
|
Fury Site Works |
|
Gary Harper Constr. |
|
Santana Truck/Excav |
|
Pacific Coast |
|
Award Construction |
|
New West Devel |
|
Pellco Construction |
|
Westwater Constr. |
|
3Kings Enviromental |
|
Average Bid |
| Schedule "A" - Off-site Watermain |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
$0.00 |
#DIV/0! |
Schedule "A" - Off-site Watermain |
157,389.00 |
|
159,030.00 |
|
158,190.00 |
|
159,952.15 |
|
204,784.00 |
|
156,525.00 |
|
200,220.95 |
|
190,477.00 |
|
256,743.00 |
|
229,985.00 |
|
244,555.00 |
|
227,984.00 |
|
195,486.26 |
| Schedule "B" - On-site Access Road, Watermain and Utilities |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
$0.00 |
#DIV/0! |
Schedule "B" - On-site Access Road, Watermain and Utilities |
271,632.00 |
|
293,405.00 |
|
275,887.50 |
|
302,325.68 |
|
298,233.00 |
|
333,655.00 |
|
327,060.00 |
|
361,535.00 |
|
316,210.00 |
|
338,000.00 |
|
321,225.00 |
|
392,430.00 |
|
319,299.85 |
| Schedule "C" - General Items |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
$0.00 |
#DIV/0! |
Schedule "C" General Items |
|
50,800.00 |
|
36,250.00 |
|
56,410.00 |
|
52,333.00 |
|
49,700.00 |
|
70,600.00 |
|
60,325.00 |
|
58,000.00 |
|
55,051.00 |
|
78,500.00 |
|
86,900.00 |
|
80,250.00 |
|
61,259.92 |
|
|
|
|
|
|
|
|
$0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Sub-total Before Local Sales & Use Tax |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
$0.00 |
#DIV/0! |
Sub-total Before Local Sales & Use Tax |
479,821.00 |
|
488,685.00 |
|
490,487.50 |
|
514,610.83 |
|
552,717.00 |
|
560,780.00 |
|
587,605.95 |
|
610,012.00 |
|
628,004.00 |
|
646,485.00 |
|
652,680.00 |
|
700,664.00 |
|
576,046.02 |
| Local Sales & Use Tax (9.5%) |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
$0.00 |
|
Local Sales & Use Tax (9.5%) |
|
45,583.00 |
|
46,425.08 |
|
46,596.31 |
|
48,888.03 |
|
52,508.12 |
|
53,274.10 |
|
55,822.57 |
|
57,951.14 |
|
59,660.38 |
|
61,416.08 |
|
62,004.60 |
|
66,563.08 |
|
54,724.37 |
| Total Project Cost including SST |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
$0.00 |
#DIV/0! |
Total Project Cost including SST |
|
525,404.00 |
|
535,110.08 |
|
537,083.81 |
|
563,498.86 |
|
605,225.12 |
|
614,054.10 |
|
643,428.52 |
|
667,963.14 |
|
687,664.38 |
|
707,901.08 |
|
714,684.60 |
|
767,227.08 |
|
630,770.40 |
| 5% Witholding (on Subtotal before SST) |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
|
|
Contractor Total |
|
|
526,728.95 |
|
535,252.43 |
|
537,083.81 |
|
563,498.86 |
|
600,691.82 |
|
614,054.10 |
|
647,368.93 |
|
667,963.14 |
|
687,664.38 |
|
712,845.00 |
|
724,539.60 |
|
767227.08 |
|
|
| Progress Release |
|
|
|
|
$0.00 |
|
|
$0.00 |
|
$0.00 |
|
$0.00 |
|
|
Difference |
|
|
-1,324.95 |
|
-142.35 |
|
0.00 |
|
0.00 |
|
4,533.30 |
|
0.00 |
|
-3,940.41 |
|
0.00 |
|
0.00 |
|
-4,943.92 |
|
-9,855.00 |
|
0.00 |
|
|
| Witholding Release on Project Completion |
|
|
|
|
|
|
|
|
|
|
|
$0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Final Total Payment |
|
|
|
|
|
|
|
|
|
|
|
$0.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|